The Ledger Letter
Finance Studio Advisors · Saturday, July 4, 2026
Market Intelligence Partner
For decades, one overlooked domestic energy source remained largely outside the investment conversation. As AI infrastructure, hyperscale data centers, and U.S. electricity demand continue accelerating, investors are beginning to revisit technologies and resources that were previously ignored.
This report explains why that shift may already be underway.
Advertisement · Behind The Markets

Two Trillion Watts Are Waiting for Permission

America can generate the power. It cannot connect it. More than 2,600 gigawatts of generation and storage projects sit in U.S. interconnection queues, per Lawrence Berkeley National Lab. That is twice the installed capacity of the entire American grid. The median wait from application to commercial operation: five years. The hyperscalers committed over $700 billion to data centers. They did not budget for the wires.
The Breakdown
Today’s disagreement: the market priced AI compute at 40 times earnings. It priced the power to run it at a fraction. It has not priced the transmission to deliver either. The queue says that takes five years.
01
The Queue
Roughly 8,200 projects totaling 2,600 gigawatts of generation and storage are seeking grid interconnection in the U.S. Only 21 percent of projects that applied between 2000 and 2019 reached commercial operation. Eighty percent withdraw, often because grid-upgrade costs consume 30 to 37 percent of total project budgets.
02
The Price
PJM’s latest capacity auction cleared at $333.44 per megawatt-day for the third straight auction. Total cost: $16.4 billion. PJM’s Independent Market Monitor found data-center demand added $23 billion in auction costs over the last three rounds. Your electricity bill is rising because cheaper power cannot get connected fast enough.
03
The Shortfall
PJM fell 6,625 megawatts short of its reliability target. Peak demand is projected to grow 32 gigawatts by 2030. All but 2 gigawatts of that is data centers. Only 2.7 gigawatts of new generation came online in the twelve months before the last auction. The math does not close.
By the Numbers
Interconnection Queue Backlog2,600+ GW
U.S. Installed Grid Capacity~1,280 GW
Median Queue-to-COD Wait5+ years
PJM Capacity Price (2027/28)$333/MW-day (cap)
PJM Auction Cost (2027/28)$16.4 billion
Queue Completion Rate21%
Sources: Lawrence Berkeley National Lab, PJM Interconnection, PJM Independent Market Monitor, EIA. Figures as of latest available.

The Binding Constraint Nobody Budgeted For

The Queue That Outlasts the Capex Cycle

In 2008, a power project took less than two years to reach commercial operation. By 2025, that median stretched past five years. The queue did not swell because demand was unusual. It swelled because the grid’s study process was designed for dozens of coal plants, not thousands of solar arrays filing simultaneously.

Active queue volume dropped 10 percent last year. Not because projects got built. Because they withdrew.

What $23 Billion in Auction Costs Tells You

PJM Interconnection serves 67 million people across 13 states. Three straight capacity auctions have cleared at the FERC-approved price cap. Without the cap, the 2027/28 auction would have cleared near $530 per megawatt-day. Sixty percent higher than what ratepayers already pay.

PJM’s Independent Market Monitor traced the cause: data centers added $23 billion in capacity costs over three auctions. The demand is real. The supply response is stuck in a queue.

Our view: the generators already connected to the grid are the beneficiaries. Constellation cleared 17,950 megawatts in the latest auction and stands to collect roughly $2.2 billion in capacity revenue. That is the premium for having wires that already reach the grid.

The Labor Market Connection

Thursday’s jobs report is part of this story. The economy added 57,000 jobs. Construction was flat. Manufacturing was flat. The sectors that build grid infrastructure did not hire.

In this tape, the hyperscalers committed the capital. The generation is being built. But the physical workforce to lay transmission lines and upgrade substations is not expanding. MISO approved a $22 billion portfolio of transmission projects across its Midwest subregion. Dominion Energy landed a $4.8 billion high-voltage direct-current project in Virginia. The money is committed. The workers are not in the pipeline. That extends the timeline.

Where the Capital Is Moving

The hyperscalers are not waiting for the queue. Google, Meta, and Amazon are signing direct power agreements that bypass the congestion. Fervo’s $2.2 billion geothermal IPO. Google’s 3-gigawatt framework deal. Meta’s 150-megawatt waterless geothermal contract in New Mexico. These are behind-the-meter arrangements designed to sidestep the bottleneck entirely.

Worth watching: PJM is developing frameworks that would let data centers connect without a guarantee of capacity during peak events. They would accept curtailment risk in exchange for faster access. That is a structural admission: the grid cannot serve everyone at once. The queue is no longer a permitting delay. It is a rationing mechanism.

What Monday Opens To

Markets are closed through the holiday. Monday, the SpaceX Nasdaq-100 inclusion forces passive buying. That mechanical event arrives into a labor market that just printed 57,000 jobs and a participation rate at a five-year low. The bond market is repricing the hike path. The power market is repricing who gets to connect. Both are about the same thing: the gap between what was promised and what the infrastructure can deliver.

The grid was built to move coal power to cities. It was not built to move drill-site steam to data centers. Two trillion watts are waiting in line. The market priced the chips. Then it priced the kilowatts. The wires are next.
The Ledger Letter
When markets disagree, the signal is in the disagreement.
This newsletter is for informational purposes only and does not constitute investment advice. Past performance is not indicative of future results.

Recommended for you